This project was awarded to Green Mountains on 24th of September 2024 for a total value of AED 1,248,140.46. We commenced the services by 27th October 2024 and completed on 26th March 2025. The scope was to load and dispose construction waste to EAD approved landfill. The total quantity was around 53,000 tons. We had full time project supervisor, part time HSE officer, Shovel Operator, Excavator operator and 2 banksmen along with 4 Green mountains tippers trucks to start with and at the later stage we used additional trucks. At the finishing stage we had up to 8 trucks in operation daily. The project was completed exceeding expectations and was a success story in a very sensitive location.